Pass4itsure Cisco (CCNA, CCNP, Meraki Solutions Specialist, CCDP…) dumps updates throughout the year and share some exam questions for free to help you 100% pass the exam

Tag: pmi 002 pdf

PMI-002 PDF, Buy Latest PMI-002 VCE UP To 50% Off

Welcome to download the newest Flydumps pmi-002 dumps

FLYDUMPS PMI-002 exam sample questions that we can provide are based on the extensive research and real-world experiences from our online trainers, with over 10 years of IT and certification experience. PMI-002 exam sample questions, including PMI-002 questions and answers feed into our customers. FLYDUMPS PMI-002 exam sample questions covers all the practice test objectives to pass PMI-002 exam. The PMI-002 exam sample questions as well as our other PMI-002 exam training tools are not only priced to be easy on your budget – but each one is also backed with our guarantee. FLYDUMPS guarantees that after using our Riverbed certification training tools, you will be prepared to take and pass your PMI-002 exam.

QUESTION 71
The project baseline is _______.
A. Original plans plus the approved changes
B. Important in the project initiation phase
C. Initial estimates for tasks and resource utilization
D. Original plans and the approved major changes
Correct Answer: A Explanation
Explanation/Reference:
Explanation:
The project baseline: original plans plus the approved changes.

QUESTION 72
Which of the following is not a form a leadership power?
A. Compromise
B. Smoothing
C. Foimal
D. Coercive Correct Answer: B
Explanation Explanation/Reference:
Explanation:
smoothing is a conflict resolution technique, the rest are forms of leadership power.

QUESTION 73
___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.
A. Procurement Management
B. Planning Management
C. Scope Management
D. Control Management Correct Answer: A
Explanation Explanation/Reference:
Explanation:
Procurement Management is groups of processes required to purchase or acquire the products, services,

 » Read more about: PMI-002 PDF, Buy Latest PMI-002 VCE UP To 50% Off  »

PMI PMI-002 Study Guide, Download Latest PMI PMI-002 PDF&VCE Covers All Key Points

Welcome to download the newest Examwind 1Z0-047 dumps:

Flydumps is providing complete solutions for PMI PMI-002 that will help the candidates learn extensively and score exceptional in the PMI PMI-002 exam. Passing the Microsoft is not a dream anymore as our user friendly learning resources ensure guaranteed success.

QUESTION 36
The work breakdown structure is ________.
A. Used to break down the project into manageable pieces
B. Set and does not change throughout the project
C. Needed as part of the project charter
D. [Needed as part of the project scope statement
Correct Answer: A Explanation
Explanation/Reference:
Explanation:
Work Breakdown Structure (WBS): A deliverable-oriented grouping of project elements which organizes and defines the total scope of the project. It sub divide the major tasks to minor details.
QUESTION 37
If a project with a SPI of 1.8, what you tell?
A. The project is running ahead of the schedule
B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None
Correct Answer: A Explanation
Explanation/Reference:
Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule performance index of 1 or greater suggests that the project is ahead of schedule.
QUESTION 38
You are managing a project that will implement a new MARKETING software package. You have assigned the resources and want to keep the IT manager in the loop by informing him or her of your decisions. Which type of organizational structure are you working in?
A. Pi’ojectized
B. Strong Matrix
C. Weak Matrix
D. Functional
Correct Answer: B Explanation
Explanation/Reference:
Explanation:
Projectized Organization: Any organizational structure in which the project manager has full authority to assign priorities and to direct the work of individuals assigned to the project. Strong Matrix: The project manager is assigned full time and has a full time support staff. Project manager has the preeminent position of authority. Weak Matrix: Power reset with Functional Manager. Functional: In this organization Project Manager has least power and all management is taken care by functional manager like marketing engineer, sales engineer.
QUESTION 39
At what point in a project do you have the highest probability that it will fail?

 » Read more about: PMI PMI-002 Study Guide, Download Latest PMI PMI-002 PDF&VCE Covers All Key Points  »